HomeMy WebLinkAboutResolution - 86-192 - Approving Schedule of Permanent Construction for Valley View Road Improvements - CITY OF FDFN PRAIRIE
HENNEPIN COUNTY , MINNESOTA
RESOLUTION 86-192
RESOLUTION APPROVING SCHEDULE OF PERMANENT CONSTRUCTION
FOR VALLEY VIEW ROAD IMPROVEMENTS
WHEREAS , the City of Eden Prairie has caused plans and specifications to be
prepared for the improvement of Valley View Road between CSAH 4 and Mitchell
Road including permanent pavement , curb and gutter, storm sewer and other
miscellaneous appurtenances ;
WHEREAS , due to an impending abandonment of the Chicago & Northwestern
Railroad 'line and the necessary correction of some poor soils in the
alignment , necessitating that work proposed between Station 39+00 and Station
53+59 will necessarily be temporary it nature.
NOW , THEREFORE , BE IT RESOLVED by the Eden Prairie City Council that the
following schedule and sequences of events to provide for permanent
construction between Stations 39+00 and 53+59 along Valley View Road are
hereby adopted;
A. Surcharge construction from 39+00 to 48+00 includes an overlay on
existing Valley View Road to carry traffic adjacent to the surcharge
fill area . The surcharge will remain for a period of 1 112 to 2
years , after which , the construction of a permanent 52 ' section will
occur. ( Including removal of the existing box culvert and temporary
CMP extensions) .
B. A temporary connection between Stations 48+00 and 53+59 to provide a
second lane of roadway through the railroad separation with the
C .N.W.R.R. shall be accomodated by means of a temporary tressle , or
with permission of the railroad company, and open cut without the
tressle.
C . Upon completion of the abandonment process by the C .N.W.R.R. , the City
will remove the existing structure for the grade separation , and let a
contract to construct a 52 ' permanent roadway section . It is expected
that the City would let a contract to construct the temporary tressle
or receive approval from the railroad company to open cut the area and
provide for the temporary connection within 6 months.
D. The anticipated time period to accomodate the abandonment of the
railroad and provide permanent roadway construction is approximately 2
years . It is the intention of the City to coordinate the permanent
construction through the surcharge area and the railroad right-of-way
into 1 contract .
ADOPTED by the Eden Prairie City Council on August 5 , 1986.
Mayor Ga D. to on